MTCC completes 80% of the K. Maafushi Island Land Reclamation and shore protection project.

In addition to this, rock boulders required for revetment works have been delivered to the project site on March 31.

The Land Reclamation and shore protection project of Maafushi island project was handed over to MTCC by the Ministry of Planning, Housing, and Infrastructure. The estimated value of the project is MVR 99.9 million.

The K. Maafushi Land Reclamation and Shore Protection project consists of, 25 hectares of land reclamation, construction of a 1,100m rock boulder revetment. The project design is based on bringing a solution to the high demand for residential plots on the island.